fbpx

Westwood Town Hall Park Construction

Construction site at Westwood Town Hall Park.

Westwood Town Hall Park Construction

The Westwood Town Hall Park project construction is continuing. Early in the construction process it was found that further engineering was required and the storm water tank had to be re-positioned on site. The underground storm system needs to be built prior to the rest of the project. This, coupled with a particularly wet August and September had slowed work on site. However, site demolition is now complete and the tank has now arrived at the site allowing further work to proceed. The contractor is exploring ways to now speed up construction and recapture at least some of the time lost. Completion is still expected by this Spring.